Geothermal Energy and Underground Renewable Resources in the Philippines — Why the World's No. 3 Geothermal Power Struggles to Grow
Editor's note: This article covers a field in which the site's operating company has business interests. It is compiled from publicly available and primary sources.
0. How to Use This Document (A Shared Note on Number Definitions)
Discussions of underground resources go wrong easily when different "types" of numbers get mixed up. The following cautions apply equally to geothermal energy, groundwater, and CCS.
| Term | Meaning | How it's used in geothermal |
|---|---|---|
| Reserves | Quantities confirmed by drilling and testing, verified as recoverable under known technical and economic conditions | In the Philippines, one assessment puts "proven" reserves at roughly the 2,500 MW class (discussed below; primary source unconfirmed) |
| Resources | Quantities geologically inferred to exist, but whose economic or technical recoverability is unconfirmed | The oft-cited "over 4,000 MW of potential" falls closer to this category |
| Endowment / potential | A theoretical estimate of the heat/capacity present in a given area | The "4,054 MW" and "4,064 MW" figures published by the DOE and others belong to this category |
注 Pitfall #1: The "roughly 4,000 MW (4,054 MW / 4,064 MW)" figure frequently cited for Philippine geothermal is a resource potential, not a confirmed reserve guaranteed to materialize once drilled. Market overviews and related literature published by ThinkGeoEnergy repeatedly frame the actually confirmed scale as roughly the 2,500 MW class, with the existing major fields (Tiwi, Mak-Ban, Palinpinon, Tongonan) already largely commercialized (source: ThinkGeoEnergy / the ScienceDirect chapter "The Philippines: Antecedents and Perspectives of the Third Largest Geothermal Power Market." The original primary-source text could not be confirmed).
注 Pitfall #2: Reporting standards used for mineral resources, such as JORC or NI 43-101, do not apply directly to geothermal energy. Geothermal resources are assessed using the "stored heat / volumetric method" or numerical simulation, and international classification frameworks such as UNFC exist, but most figures published in the Philippines are estimates from the government (DOE) or PNOC-affiliated agencies, or claims made by operators. This is a different kind of information from a third-party-audited mineral reserve report.
注 Pitfall #3: "World No. 2 / No. 3" is almost always a ranking by installed capacity (MW). The ranking can shift when measured by generation output (GWh) or by share of the power mix. Rankings also vary by several hundred MW depending on the data source (ThinkGeoEnergy / Global Energy Monitor / national governments).
1. The Philippines' Global Standing (as of Year-End 2025)
The global geothermal installed-capacity ranking at year-end 2025, published by ThinkGeoEnergy, is as follows.
| Rank | Country | Installed capacity (MW, year-end 2025) |
|---|---|---|
| 1 | United States | 3,953 |
| 2 | Indonesia | 2,742 |
| 3 | Philippines | 2,034 |
| 4 | Türkiye | 1,797 |
| 5 | New Zealand | 1,259 |
| 6 | Kenya | 980 |
| 7 | Mexico | 976 |
| 8 | Italy | 916 |
| 9 | Iceland | 808 |
| 10 | Japan | 607 |
| — | World total | 17,173 |
(Source: ThinkGeoEnergy, "Global Top 10 Geothermal Power Countries at Year-End 2025")
- The top 10 countries account for over 93% of global installed capacity.
- The Philippines' 2025 increment came from the new Tanawon plant within the BacMan II complex.
- 注 For the same year-end 2025 point, citations also circulate putting the US at 3,734 MW (on a Global Energy Monitor basis). The US figure swings by more than 200 MW depending on the source, but every source agrees the Philippines ranks third.
How It Slid from No. 2 to No. 3
| Period | Event |
|---|---|
| July 1977 | A 3 MW wellhead unit began operating on Leyte island (the country's first geothermal power) |
| 1979 | A 110 MW-class unit began operating at Tiwi (Albay Province), marking the start of large-scale development |
| 1980s–1990s | Tongonan, Malitbog, Mahanagdong, Palinpinon, and Mt. Apo came online one after another |
| 2000s onward | New development effectively stalled ("Even with the RE law, additions since 2007 amounted to only 86 MW" — a remark attributed to DOE Undersecretary Rowena Cristina Guevara) |
| 2018 | Overtaken by Indonesia, dropping from world No. 2 to No. 3 |
| 2024–2025 | Slight increases from Palayan Binary (29 MW, 2024) and Tanawon (22 MW, 2025) |
Energy Secretary Sharon Garin said in 2025, regarding the decline in ranking, "The risks are too great. That's why we fell from world No. 2 to No. 3" (source: ThinkGeoEnergy / Philippine News Agency). The government has set reclaiming second place as a goal.
2. Standing in the Domestic Power Mix — Installed Capacity and Generation Share
Installed capacity (DOE-based data)
| As of | Total domestic installed capacity | Of which geothermal | Coal | Total renewables |
|---|---|---|---|---|
| February 28, 2025 | 30,487 MW | 1,952 MW | 13,006 MW (approx. 43%) | approx. 34% |
| July 2025 | 31,701 MW | 2,004 MW | 13,006 MW (41%) | 10,240 MW (32%) |
| August 2026 (Secretary Garin's remarks) | approx. 32.2 GW | — | — | — |
(Sources: various news reports citing DOE compilations; BOI "Renewable Energy" industry profile, March 2025; Manila Bulletin, August 11, 2026)
Geothermal's Share of the Power Mix
| Period | Geothermal's share of generation | Notes |
|---|---|---|
| 2005 | approx. 17.5% | This old figure is still being cited today |
| December 2018 | 10.5% (capacity 1,918.19 MW) | DOE |
| 2023 | approx. 9.1% | Coal 62.5%, gas 14.1%, hydro 8.7% |
| April 2025–March 2026 | approx. 8% | Coal approx. 60%, gas approx. 18%, hydro approx. 11%, solar approx. 4%, wind approx. 1% (lowcarbonpower.org compilation) |
注 Pitfall #4: The website of the National Geothermal Association of the Philippines (NGAP) still states "about 1,984 MW installed, over 17% of the power mix." But that 17%-plus figure is a level from around 2005; actual results in the 2020s sit in the 8–9% range. A Japanese-language article that writes "geothermal is 17% of the Philippines' power" would be citing a number that is 20 years out of date. Because installed capacity stayed flat while total demand grew, the share roughly halved.
3. Major Geothermal Fields and Power Plants
Philippine geothermal fields fall broadly into four groups: Luzon (Tiwi, Mak-Ban, BacMan, Maibarara), Leyte (Tongonan-Leyte), Negros (Palinpinon), and Mindanao (Mt. Apo).
3-1. Overall Map (Seven Major Fields)
| Field | Location | Main power generator | Steam supply (steamfield operator) | Approximate scale |
|---|---|---|---|---|
| Tiwi | Albay Province | AP Renewables Inc. (APRI / Aboitiz Power) | PGPC (SM Group) | Nameplate 289 MW / actual output approx. 118 MW |
| Mak-Ban (Makiling-Banahaw) | Laguna Province / Batangas Province | APRI (Aboitiz Power) | PGPC (SM Group) | Nameplate 458 MW / actual output approx. 231 MW |
| Tongonan / Leyte | Kananga, Leyte Province, etc. | EDC | EDC (in-house) | One of the country's largest complexes (discussed below; combined over 700 MW class) |
| Bacon-Manito (BacMan) | Albay Province / Sorsogon Province | EDC (Bac-Man Geothermal Inc.) | EDC (in-house) | Nameplate approx. 209.8 MW |
| Palinpinon | Valencia, Negros Oriental | EDC (GCGI) | EDC (in-house) | Approx. 192.5 MW + Nasulo 49.37 MW |
| Mt. Apo | Kidapawan, North Cotabato Province | EDC | EDC (in-house) | Approx. 106 MW (came online March 1997) |
| Maibarara | Sto. Tomas, Batangas Province | Maibarara Geothermal, Inc. (MGI) | MGI (in-house) | 32 MW |
注 On "Paranas": This research could not confirm any public information supporting the existence of a geothermal service contract or power plant at Paranas, Samar Province. Nothing matching it appears in the DOE's geothermal project listings (February/April 2025 editions) either. It should be treated as unconfirmed, and if written up, the possibility of a name mix-up (with Palinpinon, Palayan, Southern Leyte, etc.) should be suspected. Note that the "Southern Leyte Geothermal Project (25 MW)" that PGPC won in June 2026 is a project in Southern Leyte Province, not on Samar Island.
3-2. EDC's Geothermal Portfolio (Plant Details)
EDC (Energy Development Corporation) is the largest player, accounting for about 56% of domestic geothermal capacity.
| Plant | Island | Capacity | Notes |
|---|---|---|---|
| Tongonan | Leyte | 123 MW (41 MW × 3) | Came online 1983 |
| Upper Mahiao | Leyte | 134 MW | |
| Malitbog | Leyte | 232.5 MW | Came online 1996 |
| Mahanagdong | Leyte | 180 MW | |
| Optimization Leyte | Leyte | 57.2 MW | |
| Palinpinon I | Negros | 112.5 MW (37.5 MW × 3) | Came online 1983 |
| Palinpinon II | Negros | 60–80 MW | Nasuji 20 MW (preserved mode), Okoy 5 (20 MW, 1994), Sogongon 20 MW × 2 (1995) |
| Nasulo | Negros | 49.37 MW | |
| BacMan I | Albay / Sorsogon | 110 MW | |
| BacMan II | Same | 20 MW | |
| Palayan Binary | Same | 28.9–29 MW | Came online 2024 (binary) |
| Tanawon | Sorsogon | 22 MW | Came online 2025; investment approx. ₱7.0 billion; flash unit from Toshiba ESS; approx. 159,000 MWh/year; over 38,000 tons of CO2 reduction annually |
| Mindanao I | Mindanao | 52.3 MW | Mt. Apo |
| Mindanao II | Mindanao | 50.93 MW | Mt. Apo |
| Mindanao III | Mindanao | 3.6 MW |
(Sources: EDC / First Gen disclosures, ThinkGeoEnergy, BusinessWorld 2025, Daily Tribune, August 1, 2025)
EDC's ongoing investment - A ₱30 billion (approx. US$510 million) 40-well drilling program. Targets: 29 MW in 2024, 54 MW in 2025, and a cumulative +85 MW by 2026. As of June 2025, 29 of the 40 wells were complete. - Mahanagdong Binary (28 MW) and three battery storage projects (totaling 40 MWh: BacMan 20 MWh, Tongonan 10 MWh, Negros 10 MWh) are planned within 2025. - In August 2025, a plan to expand the BacMan complex by 90 MW was announced (BusinessWorld, August 4, 2025). - Amacan (Mindanao / Davao de Oro): a greenfield site won through a 2017 DOE competitive bidding process. First Gen President Francis Giles Puno said he expects 70–100 MW. EDC CEO Jerome Cainglet said the project requires an investment of about US$6 million per MW, that a commerciality decision will come in 2026, and that construction after that would take two to three years. If realized, it would be Mindanao's second geothermal project since Mt. Apo (1997).
3-3. Aboitiz Power (APRI) — Tiwi and Mak-Ban
| Item | Details |
|---|---|
| Acquisition | Acquired from the government (PSALM privatization) for US$447 million in 2009 |
| Operating entity | AP Renewables, Inc. (APRI) |
| Nameplate capacity | Tiwi 289 MW + Mak-Ban 458 MW = approx. 747 MW |
| Actual output | Tiwi approx. 118 MW, Mak-Ban approx. 231 MW / net capacity sellable to the grid is approx. 300 MW |
| New facility | Tiwi Binary Power Plant, 17 MW (gross). A closed-loop system using residual heat from the brine. EPC contractors were Ormat Technologies and Desco. Construction began January 2023. AboitizPower materials describe it as its "latest operating project," which reads as already online, but the official commercial-operation-date (COD) has not been confirmed. |
| Steam supply | PGPC. Under a 2018 Geothermal Resources Supply and Services Agreement, it committed to drilling 12 production wells over six years for a 20% output increase ("12 wells, 50 MW"). The actual drilling campaign reportedly achieved 94 MW of output recovery — double the original target. |
注 Pitfall #5: The gap between "nameplate capacity" and "actual output" is extremely large in Philippine geothermal. Tiwi's nameplate is 289 MW against actual output of about 118 MW (roughly 40%). This is due to reservoir decline, scaling, and well aging, and converting a "Philippine geothermal capacity of XX MW" figure directly into generation output will almost always overstate it.
3-4. The Chevron Exit (an Important Structural Shift)
| Period | Event |
|---|---|
| Through 2016 | Chevron held a 40% stake in Philippine Geothermal Production Company, Inc. (PGPC). PGPC supplies steam for Tiwi and Mak-Ban (a combined 692 MW class). The remaining 60%, under the constitutional nationality requirement, was held by the Philippine side (SM Group's All First Equity Holdings) |
| 2016 | Bloomberg reported Chevron was considering selling its Asian geothermal assets (Philippines and Indonesia), with the deal size estimated at up to the US$3 billion class |
| December 2016 | Chevron announced signing an SPA with the Star Energy Consortium (AC Energy plus Star Energy on the Philippine side) |
| Delay | Partner All First Equity Holdings (SM Investments) held a right of first refusal, complicating the deal on the Philippine side |
| Resolution | Ultimately settled with the Ayala/Star side transferring its 99% stake to AllFirst Equity Holdings (SM Group) |
| April 2022 | Reports said SM Investments acquired the Tiwi and Mak-Ban steamfields for ₱15.73 billion |
The result is a settled split structure: "surface power plant = Aboitiz (APRI) / underground steam = SM (PGPC)." This is a point Japanese-language articles often get wrong — Tiwi and Mak-Ban are "Aboitiz's geothermal power plants," but the entity developing the reservoir is SM-affiliated PGPC.
3-5. PGPC's (SM Group's) Offensive — The Biggest Moves of 2025–2026
- In 2025, exploration drilling began at Mt. Malinao (Albay Province) using PGPC's newly built rig "Pioneer 1." The plan envisions 49 MW initially, with up to 300 MW from the surrounding area feeding into the Luzon grid.
- Exploration targets are six areas: Daklan (Benguet), Baua-Sikaw / Cagua-Baua (Cagayan), Mt. Labo (Camarines Norte), Kalinga, Southwest Kalinga, and Mt. Malinao. ₱3 billion has been budgeted for initial exploration, with a target of unlocking an additional 250–400 MW.
- On June 1, 2026, per a notice from Secretary Garin, PGPC was named the winning bidder for Predetermined Area 2 (PDA-2) of the 5th Open and Competitive Selection Process (OCSP5) — the Southern Leyte Geothermal Project (potential 25 MW) (sources: Philstar, June 6, 2026; Inquirer Business).
- Under OCSP5, a total of nine RE projects (combined over 50 MW) advanced to detailed evaluation, with bid opening on March 30, 2026.
3-6. Other Projects
| Project | Entity | Status (as of August 2026) |
|---|---|---|
| Maibarara | MGI = PetroGreen Energy 65% / ACEN 25% / PNOC-RC 10% | 32 MW operating (M-1: 20 MW, COD February 8, 2014; M-2: 12 MW, COD April 30, 2018). The site is a mere 7.5 ha. Won the land at auction from PSALM for ₱473 million in 2025. In late July 2026, signed a 2026–27 exploration drilling contract with ThermaPrime Drilling (First Balfour, part of the Lopez Group). Starts September, targeted for completion May 2027, depth 2,100–3,000 m, three confirmed wells plus one optional well. Expansion concept of up to 40 MW |
| Biliran | Formerly: Biliran Geothermal Inc. (Emerging Power / Nickel Asia group) → Now: a consortium including AG&P Industrial | Long stalled; the plant remains unfinished. DOE materials list 50 MW and approx. US$210 million, with commerciality confirmed as of December 28, 2014. In 2024, AG&P Industrial and three other companies signed an MOU for "Biliran II," envisioning 50–70 MW, with an assessment of up to 70 MW across 11,178 ha. As of January 2026, reports say it will "start from just 5 MW" |
| Kalinga / Southwest Kalinga | Aragorn Power and Energy Corp. (APEC) + Guidance Management Corp. | A 100 MW concept. A Geothermal Service Contract was granted March 25, 2010, covering 26,139 ha (Pasil / Lubuagan / Tinglayan). Exploration well PAS-02 drilling completed in 2023. Indigenous opposition continues (discussed below). Now also listed within PGPC's exploration portfolio |
4. Why Growth Has Stalled — Five Structural Factors
4-1. Exploration Risk and Upfront Investment
| Item | Figure (year, source) |
|---|---|
| Cost per exploration well | US$6–8 million (2025, per ThinkGeoEnergy / DOE explanation). Other reporting cites US$10–12 million (2026, ThinkGeoEnergy) |
| Development cost | Approx. US$6 million per MW (EDC CEO Cainglet, 2025, regarding the Amacan project) |
| From exploration to commissioning | Exploration → commerciality decision → 2–3 years of construction. The total can run to roughly a decade |
Unlike solar or wind, the fact that a dry hole means a total loss is the biggest barrier for both companies and banks. First Gen Senior Vice President Jay Joel Soriano said, "The government has treated geothermal as an 'old technology.' That's why it went without support for a long time" (Philstar, October 29, 2025).
4-2. Many Promising Sites Sit Inside Protected Areas (NIPAS / E-NIPAS)
| Law | Content |
|---|---|
| RA 7586 (NIPAS Act, 1992) | The National Integrated Protected Areas System. 11 categories, covering about 15% of the national territory and about 1% of marine waters. Managed by a Protected Area Management Board (PAMB). 注The categories, definitions (§4), and PAMB (§11) are all provisions as amended by RA 11038 (2018), and the 1992 original text must not be cited as current law (confirmed as amended, 2026-08-26; source: RA 11038 §3, §9 original text as compiled on lawphil.net). (Added on 2026-08-26 re-confirmation) RA 11038 is not the only law amending RA 7586 — RA 10629 (2013-09-26) earlier amended §16 (the Integrated Protected Areas Fund, IPAF), allowing PAMBs to retain 75% of revenue (RA 11038 §15 opens with "as amended by Republic Act No. 10629") |
| RA 11038 (E-NIPAS Act, June 22, 2018) | Expanded legally established protected areas from 13 to 107 (about 3 million ha). Delisting or reclassifying a legally established protected area now requires an act of Congress, raising the bar for developers. The law includes a provision respecting vested property and business rights existing at the time of its enactment |
| RA 9237 (2004, Mt. Apo Natural Park Act) | While designating Mt. Apo a protected area, it excludes PNOC's geothermal reservation from the park. It expressly states that ancillary facilities such as transmission lines and substations may be built within the buffer zone with PAMB approval |
注 Pitfall #6: Writing that "the Mt. Apo geothermal facility is inside a national park" is inaccurate. RA 9237 carves the geothermal area out of (excludes it from) the park core and treats the surrounding area as a buffer zone. The park core covers 54,974 ha, with a 9,078-ha buffer.
注 Conversely, if a promising new site falls within a legally established protected area post-E-NIPAS, commercialization requires coordination at the legislative level. This is a regulatory risk layered on top of exploration risk.
4-3. Relations with Indigenous Peoples (IPRA / FPIC)
- Under RA 8371 (the Indigenous Peoples' Rights Act, IPRA, 1997), development on ancestral domain requires Free, Prior and Informed Consent (FPIC) obtained through the National Commission on Indigenous Peoples (NCIP).
- Mt. Apo: A sacred site for the Obu Manuvu (Manobo) people. 1980s plans faced fierce opposition, but a compromise was reached through royalty agreements with landholders and environmental/economic commitments. In recent years, as expansion plans reach into new ancestral domain, the tribe has demanded greater involvement in governance (Mongabay, December 2021). Some argue that "obtaining FPIC alone is not enough — discussions should start from whether an exception can be recognized as an Indigenous and Community Conserved Area (ICCA)."
- Kalinga: In 2012, the Uma people of Western Uma, Lubuagan, physically blocked a Chevron survey team. The Cordillera Peoples Alliance (CPA) pointed to deficient FPIC procedures, the provoking of inter-tribal conflict, and intensified military operations in related areas. Opposition also extends to the Southwest Kalinga and Mainit-Sadanga (Mountain Province) geothermal projects.
- Promising Philippine geothermal areas are concentrated in the Cordillera region and Mindanao, which are simultaneously areas dense with indigenous ancestral domain. This geographic overlap is a structural constraint.
4-4. Coordination with Host Local Governments and Revenue Sharing
Under RA 9513 (discussed below), the government share of geothermal revenue is 1.5% of gross income. This is split 60% national / 40% local, and 80% of the host local government's share is mandated to fund electricity-bill subsidies for residents. The direct local benefit thus takes the form of electricity discounts rather than discretionary local government revenue, which narrows the bargaining chips available for building local consensus.
4-5. Policy Priorities
- Geothermal was excluded from the Green Energy Auction Program (GEAP) for a long time. First Gen has claimed it "had to wait four rounds before a geothermal contract was included."
- Indeed, only 30.9 MW was allotted to geothermal under GEA-3 (well below the envisioned 100 MW), split between EDC's Mindanao 3 and Bago binary (9.3 MW combined) and Bac-Man Geothermal Inc.'s Tanawon (21.5 MW). Delivery period 2025–2027.
- GEA-4 (awarded November 2025, 10.2 GW total) had zero geothermal (2.2 GW onshore wind, over 4.1 GW ground-mounted solar, 2.3 GW floating solar).
- GEA-5 is dedicated to offshore wind. It began November 2025, with bids submitted August 2026. The ERC approved a GEAR ceiling price of ₱11.00/kWh on February 23, 2026.
- Geothermal becomes eligible again only under GEA-9 (planned 2027: biomass, geothermal, solar, hydro, onshore wind). On February 13, 2026, the DOE announced a 10-year pipeline putting a combined 25 GW out to auction through 2035.
5. The Legal Framework — RA 9513 and Foreign Ownership Rules
5-1. Incentives Under the Renewable Energy Act (RA 9513, 2008)
Whether it has been amended (confirmed 2026-08-26): No Republic Act amending RA 9513 could be confirmed (no entry for "amending ... 9513" in LawPhil's 2023–2026 RA listing; bills expanding net metering and rooftop solar are under Senate deliberation, with a joint hearing held April 30, 2026). What has changed is not the law itself but the overlapping layers of implementing rules and tax regimes. - DOE Department Circular DC 2022-11-0034 (signed 2022-11-15 / effective 2022-12-08) amended the IRR to remove the foreign-equity restriction (see 5-2 below). It did not amend the law itself. - 注The tax incentives in the table below are grounded in RA 9513 Section 15, but they overlap with the reorganization of incentive regimes under RA 11534 (CREATE, 2021) and RA 12066 (CREATE MORE, 2024-11-11). This review could not confirm that "the CREATE-family laws expressly repealed RA 9513 Section 15" — the mainstream explanation treats the two regimes as an elective choice. Check with a tax professional on applicability to any specific project; do not use the table below alone as a current, definitive tax conclusion.
| Incentive | Content |
|---|---|
| Income Tax Holiday (ITH) | Exemption from national income tax for 7 years from the start of commercial operations |
| 10% corporate tax | 10% of net taxable income after the ITH ends (substantially below the standard rate), conditional on passing the tax savings through to consumers via lower electricity rates |
| ITH extension | Additional investment or new resource discoveries are treated as new investments. Extensions for the additional-investment portion apply up to three times the original ITH, for a cumulative maximum of 21 years |
| Import duty exemption | Duty-free import of machinery, equipment, and materials |
| Zero VAT rate | Sales of RE-sourced power are zero-rated |
| Real property tax cap | Real property tax on civil works, equipment, etc. is capped at 1.5% of the book value (original cost less accumulated depreciation) |
| NOLCO | Net operating losses incurred within 3 years of commercial operations may be carried over for 7 years |
| Local-procurement incentive | A 100% tax credit equivalent to VAT and duties for locally manufactured RE equipment, etc. |
Procedure: registration/accreditation with DOE-REMB → DOE Certificate of Endorsement → BOI registration. BIR Revenue Regulation No. 7-2022 (June 22, 2022) established the operational guidelines.
Government share (Sec. 13): 1% of gross income for RE generally; 1.5% for geothermal ("indigenous geothermal") alone. Community-scale micro projects of 100 kW or less are exempt, and biomass carries no government share.
5-2. The 2022 Opening to 100% Foreign Equity — Geothermal Is "Excluded"
| Item | Content |
|---|---|
| Basis | Department of Justice Opinion No. 21 (2022): interpreted solar, wind, hydro, and ocean (tidal) power as falling outside the nationality requirement of Constitution Article XII, Section 2 |
| Circular | DOE Department Circular No. 2022-11-0034 (signed November 15, 2022; effective December 8, 2022). Amended Section 19 of RA 9513's IRR |
| Effect | Enabled 100% foreign equity in the exploration, development, and utilization (EDU) of solar, wind, hydro, and ocean energy. Foreign partners in existing joint ventures may also buy out the Philippine side's stake |
| Excluded | Geothermal is excluded. Drawing water from natural sources is also excluded (water is classified as a "depletable resource") |
注 Pitfall #7 (the most important one on this topic): "The Philippines opened renewables to 100% foreign ownership in 2022" → "so geothermal can also be entered with 100% foreign equity" is wrong. Geothermal remains subject in principle to 60% Filipino ownership. In its own explanation of the 5th Open and Competitive Selection Process (OCSP5), the DOE explicitly states, "OCSP contracts are open to both Filipino and foreign companies to bid on. Geothermal is an exception, however, requiring a corporation at least 60% Filipino-owned and Filipino-controlled."
5-3. The Exception Route = FTAA (Large-Scale Geothermal)
| Item | Content |
|---|---|
| Timing | On October 20, 2020, Secretary Alfonso Cusi signed the OCSP3 guidelines |
| Content | 100% foreign equity is permitted for the exploration, development, and utilization of large-scale geothermal, via a Financial and Technical Assistance Agreement (FTAA), which the President signs |
| Definition of "large-scale" | An initial investment of approximately US$50 million or more |
| Legal basis | RA 9513 defines geothermal as a "mineral resource," and under the Constitution, FTAAs are permitted for petroleum, minerals, and mineral oils — this is the reasoning. Explained by then-NREB Chair Monalisa Dimalanta |
| Procedure | Foreign and domestic bidders alike must compete through the Open and Competitive Selection Process (OCSP) |
| Risk | Legal practitioners (such as John Yeap of Pinsent Masons) note that "the possibility of a future legal challenge is not zero." Classifying geothermal as a mineral leaves an open question of constitutional interpretation |
注 In practice, then, foreign entry comes down to two options: (1) presidential approval as an FTAA project exceeding US$50 million, or (2) a joint venture with a 60% Philippine partner. Chevron's 40% stake in PGPC reflected this constraint.
5-4. The 2025–2026 Headline — The Geothermal Resource De-Risking Facility (PGRDF)
| Item | Content |
|---|---|
| Name | Philippine Geothermal Resource De-Risking Facility (PGRDF) |
| Size | Approx. ₱10.7 billion / approx. US$170 million (exceeding the original US$100 million target) |
| Funding source | A sovereign loan from the ADB (Asian Development Bank) to the Philippine government |
| Approval | Approved by the Economy and Development Council (2025) |
| Signing | In December 2025, Secretary Garin and Landbank President Ma. Lynette Ortiz signed the MOA at the 2025 Sustainable Energy Awards in Makati |
| Launch | Available starting Q1 2026 |
| Mechanism | A "conditionally repayable grant" under which the government covers at least 50% of exploration and drilling costs. If the well succeeds, it converts to a loan (repayable); if it fails, it remains a grant (no repayment required) |
| Administration | Land Bank of the Philippines serves as Facility Administrator & Manager, disbursing funds on a milestone basis |
| Purpose | The ADB's GRDF aims to restart greenfield geothermal investment, which had been stalled since 2001 |
The resumption of greenfield drilling at Amacan (EDC) and Mt. Malinao (PGPC) is cited as a direct result of this scheme.
Related event: The 7th Philippine International Geothermal Congress, themed "Sharpening the Geothermal TIP: Technology, Investment, and Policy," is scheduled for September 2–4, 2026, in Lipa City, Batangas.
6. Targets — How High Does the Government Want to Go?
| Target | Figure | Source / year |
|---|---|---|
| RE share | 35% by 2030, 50% by 2040, over 50% by 2050 | Philippine Energy Plan (PEP) 2023–2050 |
| Geothermal capacity | 3,000 MW by 2030 (requiring approx. US$1.5 billion in investment) | DOE (2025–2026 media reports) |
| Geothermal additions | 2.5 GW of new geothermal by 2040 | PEP-related (via media) |
| Total installed capacity | 121.3 GW needed by 2040 (vs. approx. 32.2 GW currently — roughly a 276% increase) | DOE, Secretary Garin's post-SONA press briefing, August 11, 2026 (Manila Bulletin) |
| Near term | Of a 10,000 MW pipeline, 4,100 MW is scheduled for completion | Secretary Garin, early August 2026 |
注 Market analysts, meanwhile, are less optimistic. Because "confirmed geothermal reserves are largely already commercialized, and unconfirmed resources sit in harder-to-access locations," one outlook projects geothermal's generation share falling to 8% by 2030 and 4% by 2040 (per a market overview published by ThinkGeoEnergy). That is a large gap from the 3,000 MW target.
注 Pitfall #8: Even as of August 2026, while geothermal is relied on as a "stable power source" in grid operations, outages also have a large impact. In August 2026, the shutdown of Cebu Private Power Unit 10 and a drop in Leyte-A geothermal output contributed to extending a yellow alert on the Visayas grid.
7. Other Uses of the "Underground" Besides Geothermal
7-1. Groundwater and the Sinking of Metro Manila
| Indicator | Figure (year, source) |
|---|---|
| Maximum subsidence rate | 109 mm/year (about 11 cm), in Bulacan Province (industrial/residential areas around Guiguinto, Balagtas, Bulakan). Sentinel-1 InSAR, 2014–2020. UP Diliman (Jolly Joyce Sulapas, Audrei Anne Ybañez, Alfredo Mahar Francisco Lagmay, et al., UPRI-NOAH) |
| CAMANAVA (Caloocan, Malabon, Navotas, Valenzuela) | 10–20 mm/year (areas with groundwater regulation) |
| Bulacan and Cavite Provinces | Over 40 mm/year (areas outside regulation) |
| Coastal localized maximum | 2–11 cm/year, locally 10–15 cm/year (2014–2020). Effective relative sea-level rise reaches over about 2.6 cm/year in some areas (2025 study published in MDPI) |
| For comparison: global average sea-level rise | About 3.7 mm/year |
In other words, the "rate of sinking" around Metro Manila is 10 to 30 times the pace of sea-level rise from global warming. UP researchers (Fernando Siringan, Carlo Arcilla) have concluded that "the main cause of Manila sinking is not warming but the over-extraction of groundwater for household and commercial use."
Regulatory framework
| Item | Content |
|---|---|
| Legal basis | PD 1067 (the Philippine Water Code) |
| Regulator | NWRB (National Water Resources Board), coordinating with the DENR and local governments |
| Key measure | NWRB Resolution No. 001-0904 (2004) imposed a moratorium on new deep wells, revoking water rights in eight initially designated critical areas — Bulacan Province (Guiguinto, Bocaue, Marilao, Meycauayan), North Caloocan, West Navotas, Quezon City, Makati, Mandaluyong, Pasig, Pateros, Parañaque, Pasay, Las Piñas, Muntinlupa, and Dasmariñas, Cavite. It was later extended to all of Metro Manila and parts of Rizal Province |
| Status (2025) | All of Metro Manila and parts of Bulacan, Cavite, Rizal, and Laguna are designated "critical / over-extracted." Existing permits remain valid, but renewals face strict review |
| Enforcement record | 1,008 illegal or abandoned deep wells closed between 2008 and 2013 (NWRB) |
| Exception | During droughts or El Niño events, there have been instances of temporarily reopening closed wells, under NWRB supervision, for critical facilities such as hospitals |
Saltwater intrusion is also severe. Chloride concentrations exceed drinking-water standards in shallow layers and the upper confined zone along the Manila Bay coast. In the Marikina Valley, saltwater is reached at depths below 180 m; east of the Pasig-Marikina river confluence, it is reached at around 50 m. Seepage from the Pasig River is also a pathway.
注 Pitfall #9: The 2022 opening to 100% foreign equity does not extend to "groundwater." The Department of Justice held that inland waters such as rivers and lakes are depletable resources, so the Water Code's nationality requirement continues to apply (ocean and tidal power are treated as excluded from it). Writing that "the Philippine water business is open to 100% foreign ownership" is incorrect.
7-2. CCS (Underground Carbon Storage) — Still at the Study Stage
| Item | Status (as of August 2026) |
|---|---|
| Dedicated legislation | No law governing CCS/CCUS, nor any comprehensive DOE CCS regulation, could be confirmed to exist in the Philippines (unconfirmed = likely does not exist) |
| Congress | In the 19th Congress, Proposed Senate Resolution No. 40 called for a legislative inquiry into CCS technology — the most concrete legislative action to date |
| Regional comparison | Malaysia introduced a CCUS bill in March 2025, proposing a CCUS agency and a licensing system for onshore and offshore storage. The Philippines is well behind |
| Storage potential | An ADB (2013) study of four regions (Vietnam, Thailand, Metro Manila, South Sumatra) estimated combined storage resources of 54 GtCO2 across the four. Of this, 88% is in saline aquifers, with hydrocarbon fields across 143 blocks accounting for only 3.5 GtCO2. ERIA (2024) notes that "the underlying data was never published, and the region has not been reassessed since 2013" |
| Leading candidate | The Malampaya gas field, online since 2001. 注The "about 40% of Luzon's power" figure is a past peak-period value; as of 2026 its contribution has fallen to about 20% (PCIJ, January 2026 / see the "Oil, Natural Gas, and Offshore Resources" article, §2.2). 注A "commercial depletion around 2027" was also a pre-Phase-4 projection; the success of MAE-1 (98 Bcf original reserves) and Camago-3 (about 2.5 times that) in 2026 is expected to extend operating life by roughly six years (the end date remains unsettled, with both 2030 and 2034 cited; see §2.3, 2.5 of the same article). SC 38 was renewed in 2023 and permits extraction through February 2039. The drillship Noble Viking arrived on June 19, 2025, starting Phase 4. The idea of repurposing depleted wells and platforms for CO2 storage is theoretically plausible, but no official plan for it could be confirmed (revised in a 2026-08-25 cross-check; correcting a lingering outdated figure) |
| Adjacent carbon policy | HB 11375 (the Low-Carbon Economy Investment Act) passed second reading in February 2025 but lapsed when the 19th Congress adjourned on June 30, 2025. In the 20th Congress, HB 1817 (July 14, 2025) and several others were refiled and referred to the House Committee on Climate Change. In mid-October 2025, the DOE issued a circular on general guidelines for energy-sector carbon credits |
注 Pitfall #10: Writing that "CCS projects are moving forward" in the Philippines is currently incorrect. Neither the legal framework, a regulator, nor a permitting system is yet in place; the situation remains at the level of regional studies and a legislative inquiry. It should not be treated on the same footing as Malaysia or Indonesia.
7-3. Direct Use of Low-Temperature Geothermal
ThinkGeoEnergy and others point out that the Philippines has low-temperature geothermal resources (low- to medium-enthalpy) that remain untapped. Direct use for drying, refrigeration, bathing, and the like, and small-scale binary generation, are technically feasible, and binary projects that use residual brine heat — Palayan Binary (29 MW), Tanawon (22 MW), Tiwi Binary (17 MW), Mahanagdong Binary (28 MW) — have in fact been at the center of the 2024–2025 increment. The real picture for the 2020s is that future growth potential lies less in "new large-scale fields" and more in "optimizing existing fields plus binary generation."
8. Summary — 10 Key Points to Remember
- The Philippines ranks world No. 3 in installed capacity at 2,034 MW (year-end 2025, ThinkGeoEnergy). No. 1 is the US at 3,953 MW, No. 2 is Indonesia at 2,742 MW. It was overtaken by Indonesia in 2018.
- Geothermal's share of the power mix is about 8% (April 2025–March 2026). "17%" is an old figure from around 2005 that still lingers on an industry association's website, so it is frequently miscited.
- The "roughly 4,000 MW" figure is a resource potential, not a confirmed reserve. The harsh reality is that what has been confirmed is largely already commercialized.
- Surface (power plant) and subsurface (steam) are split. At Tiwi and Mak-Ban, Aboitiz (APRI) generates power while SM-affiliated PGPC supplies steam. Chevron exited in the late 2010s.
- EDC (First Gen / Lopez Group) accounts for about 56% of domestic geothermal capacity, holding Leyte, BacMan, Palinpinon, and Mt. Apo.
- Geothermal is not included in the 2022 opening to 100% foreign equity (DC 2022-11-0034). Geothermal remains subject in principle to 60% Filipino ownership; 100% foreign equity is available only through the separate FTAA route for projects over US$50 million (2020 OCSP3).
- Protected areas (the E-NIPAS Act, RA 11038, 2018), indigenous FPIC (IPRA, 1997), local government coordination, and exploration risk (US$6–12 million per well) are the four major factors behind the stagnation.
- Starting Q1 2026, the ADB-funded US$170 million "Philippine Geothermal Resource De-Risking Facility (PGRDF)" is operational, covering 50% or more of drilling costs through conditionally repayable grants.
- Actual developments in 2026 include PGPC's Mt. Malinao exploration and its win of the 25 MW Southern Leyte project (June), EDC's Amacan commerciality decision, and Maibarara's 2026–27 drilling campaign (starting September). Geothermal returns to the auction only with GEA-9 (2027).
- As a separate underground issue, land subsidence around Metro Manila (up to 109 mm/year in Bulacan Province) is proceeding at 10 to 30 times the rate of sea-level rise. CCS remains at the study stage, with no legal framework yet in place.